Update from Forkers Limited
Forkers Limited have remobilised to site and are underway with Phase 2 of the enabling works at Anstey’s Road, Hanham.
The new raised table has been completed to the highway at the junction of Memorial Road and New
Walk, and additional highway improvement works continue further along New Walk to manage
traffic flows and create the new goods access for Sealtech.
Further site investigation works have been undertaken and probe drilling works are currently ongoing
towards the north of the site. It is anticipated that the first phase of drilling work will be completed in
the next 1-2 weeks, with a second, shorter phase being undertaken in late August, following the
completion of Sealtech’s new access.
This current overall phase of work is estimated to be completed by mid-September.
We would like to take this opportunity to thank local people for their patience and understanding during this phase of the project.